Post Earthquake Redevelopment
Programme |
| |
| |
| NC-2 6A
Progress Report |
.tmp) |
|
| POST EARTHQUAKE
REDEVELOPMENT PROGRAMME |
| |
|
|
|
|
|
|
| NC-II (Tender -
6A) |
| |
|
|
|
|
|
|
| PROGRESS REPORT |
| |
|
|
|
|
|
|
|
|
Lot No. |
District |
CMSO |
PHC |
Disp. |
SC |
SQ |
Total Strs. |
|
2 |
Rajkot-Junagadh-Jamnagar-Porbandar
(Backbone
Project Ltd.) |
0 |
8 |
2 |
3 |
15 |
28 |
|
|
Deleted Structures |
|
1 |
|
|
|
1 |
|
|
Present Scope of Work |
0 |
7 |
2 |
3 |
15 |
27 |
|
|
Handed over Structures |
|
6 |
1 |
|
8 |
15 |
|
|
Under Progress |
0 |
1 |
1 |
3 |
7 |
12 |
|
|
|
|
|
|
|
|
|
|
3 |
Janmanag-Amreli-Surat-Patan
(Shanti
Construction Co) |
5 |
0 |
0 |
0 |
0 |
5 |
|
|
Deleted Structures |
1 |
|
|
|
0 |
1 |
|
|
Present Scope of Work |
4 |
0 |
0 |
0 |
0 |
4 |
|
|
Handed over Structures |
2 |
|
|
|
|
2 |
|
|
Under Progress |
2 |
0 |
0 |
0 |
0 |
2 |
|
|
|
|
|
|
|
|
|
|
|
Total for NC - Phase I |
5 |
8 |
2 |
3 |
15 |
33 |
|
|
Deleted Structures |
1 |
1 |
0 |
0 |
0 |
2 |
|
|
Present Scope of Work |
4 |
7 |
2 |
3 |
15 |
31 |
|
|
work not started |
|
|
|
|
|
|
|
|
Handed over Structures |
2 |
6 |
1 |
0 |
8 |
17 |
|
|
Under Progress |
2 |
1 |
1 |
3 |
7 |
14 |
|
|